River Plaza Condominium

River Plaza Condominium
Chicago, IL

The River Plaza Condominium Association retained McGuire Engineers (MEPC) to complete an energy audit for its Chicago complex to determine if the replacement of existing equipment was necessary.

{tag_name_nolink}
{tag_name_nolink}

SERVICES PROVIDED

Energy Audit


ENGINEERING SOLUTIONS


  • Simulated the building using energy modeling software, and compared the actual energy use from utility bills to the simulated energy use.

  • Once the model matched the actual energy use, MEPC modeled new heating, cooling and lighting equipment and determined the simple payback for various options.

  • The results of the audit showed that the existing boilers and domestic hot water heaters could be replaced with new and more energy efficient boilers and achieve simple payback in six to seven years.


FEATURED STORIES

  • 01-Nov-2011 McGuire Engineers: Serious Impact

    Talk about putting your money where your mouth is. When it came time for new office space, the leadership at McGuire Engineers (http://www.mepcinc.com/#/home), I..

  • 01-Jun-2011 Columbia College Boiler

    Here’s a task: bridge the new mechanical room to the utility connection in the old space located in an adjacent building in Chicago’s South Loop. ..

View All Stories

FEATURED PROJECT

John Marshall Law School
Location:
Chicago, IL

Services:
Law Library Renovation
View All Case Studies